Yes Yes Nov 3 Committee
Whitefish Bay, WI
yesyesno

More than two years of study and review have gone into the Whitefish Bay School Board's unanimous decision to ask voters for bonding authority of $22.6 million for building repairs and improvements.
September 2006 - The School Board approves the creation of a District Facilities Study Committee, comprised of parents, teachers, administrators and elected school board members.
March 2007 - The Facilities Study Committee holds the first of 19 meetings, which will include tours of all district facilities, meetings with staff and architects and discussion of district priorities.
April 2007 - Bray Architects is engaged to provide technical expertise.
June 2007 - Input sessions at all schools are held to collect staff ideas and concerns. National Honor Society students participate at the high school.
January 2008 - The Faciliites Study Committee completes its research and prepares a report to submit to the School Board.
February 2008 - The facilities study is accepted by the School Board. View the report as a PDF file.
April 2008 - The School Board begins a six-month review of the study, discussing the report, touring schools and interviewing staff.
October 2008 - Presentation/Input sessions on the proposals are held for staff at each of the district schools.
October 2008 - School Board votes to delay advancement of the proposals because of the economic downturn.
February 2009 - School Board resumes work on advancing the facilities study process.
March 2009 - Bray Architects presents data to the School Board on the economic downturn's effect on projected construction costs.
April 2009 - The School Board authorizes a community telephone survey to poll 300 residents for opinions on the proposed facilities work.
May 2009 - A consensus is reached by the School Board to move forward with a referendum.
June 2009 - The results of the community survey are reviewed.
August 2009 - Listening sessions are held to receive public input on the proposals at both elementary schools and at the High School.
September 2009 - The School Board votes unanimously to place two questions on the ballot seeking to spend a total of $22.6 million for the facilities Stewardship and Educational Improvement plans.
November 2009 - Voters approve both referendum questions.
Want to endorse the plan? See "Feedback"
The Facilities Study Committee originally identified more than $40 million in repairs and improvements that members felt would be needed by district schools over the next 20 years. This became known as the "Master Plan."
Next, the committee isolated essential maintenance from the Master Plan that would keep the aging buildings sound. This came to be called the "Stewardship Option."
Finally, the committee chose the most urgent of the proposed building enhancements it had identified as an "Educational Improvement Plan," and urged the board to adopt this reduced-cost option. View the full committee report.
Stewardship Plan (Question 1 on the ballot): The School Board reduced infrastructure spending in the Stewardship Plan from $14 million to $9 million after state aid was cut by the Legislature last spring. The reduction in debt service that was to fund a portion of the Stewardship Plan was used to fund the 2009-'10 operating budget instead. Cuts were made based on a shortened time span for the plan, reduced to 10 years from 15.
Educational Improvement Plan (Question 2 on the ballot): A Middle School Fitness Center was eliminated from the plan.